OVERVIEWWilder was subcontracted to provide staffing and field leadership to maintain environmental compliance with all aspects of permits, mitigation measures, and agency guidance for installation of 88 miles of new fiber optic line during 3-year construction schedule.
SERVICES INCLUDED:Staffing of Field Project Management, teams of USFWS Authorized Desert Tortoise Biologists, and Biological Monitors
Protocol Desert Tortoise, Mojave Fringe-toed Lizard, Burrowing Owl, Desert Kit Fox, and MBTA avian surveys
Mojave ground squirrel mitigation measures implementation
Mitigation for burrowing owl and desert kit fox included surveys, camera traps, monitoring, passive relocation of animals within the project impact areas
Rare plant surveys, mitigation and transplantation of all succulents, western Joshua trees, and other Yucca spp. located in disturbance areas of project line
Noxious and Invasive weed surveys, mitigation implementation
On-site Field Techniques and Safety training as needed for new Biological Monitor hires coming from Chambers Group, Inc.
On-site Environmental Awareness Education of all project personnel
On-demand mapping (ArcGIS) of sensitive resources
Data QA/QC, archival, and synthesis of summary progress reports
Editing and support for final reporting
Services delivered included daily scheduling, staffing, training, and supervision of 10-20 biological resource monitors in coordination with activities of multiple construction subcontractors working concurrently, on three project segments, generally spanning ~70 linear miles during weekly activities.
Project Field Leadership in running all surveys and mitigation actions. Provision of data management, weekly and summary reporting, mapping, as well as guidance and consultation with foremen, project managers, third-party inspectors/monitors, and field staff of relevant government agencies (USFWS, Mojave National Preserve USDOI, CDFW, San Bernardino County).